IC 13-18-18-1
Rules
Sec. 1. The department shall establish a general coal mine permit
that may be obtained for a facility instead of obtaining another more
specialized National Pollutant Discharge Elimination System coal
mine permit.
As added by P.L.1-1996, SEC.8. Amended by P.L.81-2011, SEC.3.
IC 13-18-18-2
Criteria for consideration
Sec. 2. The department shall determine the criteria that must be
met to qualify for the general permit.
As added by P.L.1-1996, SEC.8. Amended by P.L.81-2011, SEC.4.
IC 13-18-18-3
Notice of intent
Sec. 3. The general permit established under this chapter must
allow a coal mine operator the option of submitting a notice of intent
to be governed by the general permit requirements before the
requirements apply to the coal mine operator.
As added by P.L.1-1996, SEC.8. Amended by P.L.81-2011, SEC.5.