FOR PUBLICATION
ATTORNEY FOR APPELLANT: ATTORNEY FOR APPELLEE:
JEFFREY A. MODISETT G. DANIEL KELLEY, JR.
DANIEL B. DOVENBARGER DANA G. MEIER
Attorney Generals Office Ice Miller
Indianapolis, Indiana Indianapolis, Indiana
IN THE COURT OF APPEALS OF INDIANA
INDIANA DEPARTMENT OF )
NATURAL RESOURCES )
)
Appellant, )
)
vs. ) No. 77A04-9909-CV-429
)
PEABODY COAL COMPANY )
)
Appellee. )
APPEAL FROM THE SULLIVAN CIRCUIT COURT
The Honorable P. J. Pierson, Judge
Cause No. 77C01-9805-MI-150
November 16, 2000
OPINION - FOR PUBLICATION
SHARPNACK, Chief Judge
The Indiana Department of Natural Resources (DNR) appeals the judgment of the trial
court affirming a decision of the administrative law judge (ALJ) in favor of
Peabody Coal Company (Peabody). The DNR raises four issues, which we consolidate
and restate as:
whether the trial court erred in affirming the ALJs decision that the DNR
had applied an incorrect legal standard in requiring Peabody to replace more than
topsoil for land reclamation; and
whether the trial court erred in affirming the ALJs decision that the DNR
made inadequate findings to support its determination that Peabody was required to remove
eighteen inches of soil, including both topsoil and subsoil, for land reclamation.
We affirm.
The relevant facts follow. The DNR is a state administrative agency with
responsibility for the administration and enforcement of the Indiana Surface Mining Control and
Reclamation Act (SMCRA),
See footnote a program for the regulation of surface coal mining.
Peabody is a corporation that operates surface coal mining operations under SMCRA permits
issued by the DNR. This case arises out of the refusal of
the DNR to allow a revision to four of Peabodys surface mining permits
so as to allow Peabody to remove and store for replacement eight to
twelve inches of topsoil rather than eighteen inches of combined topsoil and subsoil
as the permit required.
In 1990, it was the DNRs policy to require surface land miners to
replace and redistribute a minimum of eighteen inches of soil, which could include
both topsoil and subsoil, after mining on all non-prime farmland areas used as
cropland. On October 12, 1990, Peabody filed a request for administrative review,
under 310 Ind.Administrative Code 0.6-1-15, seeking to set aside the DNRs policy.See footnote
The ALJ determined that the most reasonable interpretation of 310 Ind.Administrative Code 12-5-12.1,
the section of the SMCRA that bears most directly on topsoil and subsoil
replacement for surface coal mining activities, was that subsoil is not generally required
to be salvaged and replaced. However, under subsection (f), which acts as
an exception to the general principle, the DNR could require subsoil to be
salvaged and replaced only if the director found subsoil replacement to be necessary
in a particular case. The ALJ concluded that without having formally promulgated
a rule in accordance with Ind. Code § 4-22-2, the DNR could not
uniformly require all miners to replace a minimum of eighteen inches of soil
after mining regardless of whether eighteen inches of topsoil existed before mining.
While that case was pending review by the trial court, the DNR and
Peabody agreed as to the permits at issue here to a condition requiring
a soil replacement depth of eighteen inches, subject to judicial review by the
trial court. Pursuant to the agreement, Peabody thereafter submitted permit revisions incorporating
the eighteen inch minimum soil replacement depth with a reservation that if the
eighteen inch policy was determined to be invalid by the trial court, it
would submit another revision to seek removal of the language.
When the trial court affirmed the decision of the ALJ that the DNR
could not impose a general minimum soil replacement depth of eighteen inches for
all cropland without having formally promulgated such a rule,See footnote Peabody sought a revision
to the permits at issue here to reduce the amount of soil it
had to replace after mining. In essence, Peabody sought to remove and
replace only the topsoil, which varied from eight to twelve inches, not the
subsoil. After reviewing Peabodys revision applications, the DNR denied the applications in
four separate, but virtually identical letters. In each of the four letters,
the DNR wrote:
The applicant proposes to restore an average of 8 to 12 inches of
topsoil on graded cast overburden for all non-prime farmland areas. Based upon
the information available to the Director, the Director finds in this specific case,
a soil replacement of 8 to12 inches is inadequate to comply with the
land capability restoration and revegetation requirements of 310 IAC 12-5. Therefore, the
Director has made a special finding that it is appropriate with respect to
this particular case to require a portion of the subsoil be removed and
segregated, and redistributed in accordance with 310 IAC 12-5-12.1 since he finds such
subsoil layers are necessary to comply with the land capability restoration and revegetation
requirements of 310 IAC 12-5.
Record, pp. 903, 905, 913, 917.
Peabody petitioned for administrative review of the DNRs denial of its requests
to reduce soil replacement depths. On April 14, 1998, the ALJ made
the following findings, in pertinent part:
(15) As specified in IC 14-34-10-2(b)(3), one of the duties of an operator
is to [r]estore the land affected to a condition capable of supporting the
uses that the land was capable of supporting before mining or higher or
better uses.
(16) The clear statutory purpose of Indiana SMCRA is to require an operator
to reclaim land to as good or better shape as it was prior
to mining.
JH&L Coal Company, d/b/a Miller Mining v. Department of Natural
Resources, 7 Caddnar 28 (1994). To that end, unless a site is
restored to the same use as existed prior to mining, the site must
be restored to a higher and better use. A corollary is that
the approved postmining land use for a particular site is either the same
as, or better than, the premining land use.
(17) The special finding made by the DNR for the subject permits requires
a two-prong standard be met in order for an operator not to provide
18 inches as a standard soil replacement. Reference is made both to
land capability restoration and to revegetation requirements.
(18) . . . compliance with the revegetation requirements for the approved postmining
land use is a cornerstone of Indiana SMCRA. Since the approved postmining
land use is either the same as or better than the premining land
use, compliance with the revegetation requirements assures an operator must reclaim the land
to as good as or a better condition than existed prior to mining.
(19) In the Peabody cases, the approved postmining land use is cropland.
Revegetation requirements must be measured within the context of cropland. . . .
(20) No general land capability standard is set forth in 310 IAC
12-5-12.1(f), however, apart from the revegetation requirements in 310 IAC 12-5-59, 61, 62,
63, and 64.1. Soil replacement, land use, and revegetation are inextricable.
Attainment of the approved postmining land use, as demonstrated by compliance with the
revegetation requirements for that land use, insure that the land will be restored
to a condition capable of supporting that use. 310 IAC 12-5-68 requires
an operator reclaim either to the land use which existed prior to mining
or to another approved higher and better use. Section 68 does not
require an operator to establish land capability of the approved postmining land use,
as well as a variety of other land uses. The land capability
of the two-prong test sought to be established by the DNR in the
special finding is not supported by Indiana SMCRA.
(21) The documentation listed by the DNR in support of each special finding
is general and pervasive. Soil types are listed. Literature is listed.
Nowhere does the DNR provide findings which are derived from specific postmining
land uses. The broad sweep of these special findings precludes administrative review.
The broad sweep of these special findings does not comport with the
narrow, precise strokes anticipated by the regulatory structure and embodied most directly by
310 IAC 12-5-12.1(f).
(21) [sic] The DNR has the burden of going forward to show under
310 IAC 12-5-12.1(f) that the land to be reclaimed under the subject permits
embodies those limited circumstances where additional soils from subsoil layers are needed to
comply with the revegetation requirements of 310 IAC 12-5 for the approved postmining
land use. The documentation in the record fails to meet the burden
because it fails to provide the site specificity anticipated by 310 IAC 12-5-12.1(f).
The documentation in the record also fails to meet the burden because
it applies a standard not set forth in 310 IAC 12-5-59, 61, 62,
63 or 64.1 for approved postmining land uses. The DNRs special finding
exemplified by Permit S-246 is a template which could be applied to all
non-prime farmland, resulting in universal application of the 18-inch soil replacement minimums.
Public policy may support a universal 18-inch soil replacement minimum, but if so,
it is a public policy properly embodied by rule or statute.
Record, pp. 980-981. The ALJs final order is as follows:
Each of the permits at issue . . . is remanded to the
[DNR] so that it may determine whether portions of the subsoil should be
removed and segregated, stockpiled and redistributed as subsoil in accordance with 310 IAC
12-5-12.1(d) and (e), where the portions are necessary to comply with the revegetation
requirements of 310 IAC 12-5-59, 310 IAC 12-5-61, 310 IAC 12-5-62, 310 IAC
12-5-63, and 310 IAC 12-5-64.1. Any determination must be site specific and
must include soil analysis by a qualified professional which demonstrates that soil replacement,
in addition to existing topsoil, is needed to achieve the revegetation requirements of
the approved postmining land use.
Record, p. 982.
The DNR appealed the decision of the ALJ, contending that the ALJ had
erroneously placed the burden on the DNR to show that additional soils from
subsoil layers were necessary and erroneously determined that the DNRs findings were insufficient
to support its determination that Peabody needed to replace eighteen inches of topsoil
in order to reclaim the land. On review, the trial court affirmed
the ALJs findings and conclusions.
The Indiana Administrative Orders and Procedures Act governs this case. See Ind.
Code §§ 4-21.5-1-1 to 4-21.5-6-7. Upon judicial review of an agency order,
a trial court is limited to determining whether the agencys action is:
arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law;
(2) contrary to constitutional right, power, privilege, or immunity;
in excess of statutory jurisdiction, authority, or limitations, or short of statutory right;
(4) without observance of procedure required by law; or
(5) unsupported by substantial evidence.
I.C. § 4-21.5-5-14(d). The burden of demonstrating the invalidity of the agency
action is on the party who is asserting the invalidity. Peabody Coal
Co. v. Indiana Dept of Natural Res., 629 N.E.2d 925, 928 (Ind. Ct.
App. 1994), summarily affd, 664 N.E.2d 1171, (quoting State Prison & State Employees
Appeals Commn v. Van Ulzen, 567 N.E.2d 1164, 1166-1167 (Ind. Ct. App. 1991),
vacated on other grounds, 582 N.E.2d 789).
Neither a trial nor an appellate court reviewing an administrative determination may reweigh
the evidence or judge the credibility of witnesses. Id. Both must
accept the facts as found by the administrative body. Id. However,
because law is the province of the judiciary, we need not accord the
same degree of deference to an agencys conclusion on a question of law.
Id. Thus, [a]n interpretation given a statute by an administrative agency
charged with the duty of enforcing the statute is entitled to great weight;
however, an agencys interpretation of a statute which is incorrect is entitled to
no weight. Id. While the reviewing court may not reweigh the
evidence that was before the administrative agency, it may reverse the agencys finding
if it is contrary to law. Id. Similarly, if an agency
misconstrues a statute and there is no reasonable basis for the agencys ultimate
action, the agencys action may be reversed on review as being arbitrary and
capricious. Id.
Generally, the rules that apply to the construction of statues also apply to
the construction of administrative rules and regulations. Id. at 930. In
construing an administrative regulation, words must be given their plain and ordinary meaning.
Id. The court must look to the regulation as a whole
and to its object and policy rather than placing emphasis on a single
sentence or a part thereof. Id. As with statutes, [a]n interpretation
by an administrative agency charged with the duty of enforcing the applicable statues
and regulations is entitled to great weight; however an agencys interpretation which is
erroneous is entitled to no weight. Id.
310 IAC 12-5-12.1(f). As held by the ALJ and affirmed by the
trial court, the plain language of 310 IAC 12-5-12.1(f) indicates that a miner
is not required to remove and replace subsoil unless the director of the
DNR finds such is necessary to meet the revegetation requirements.
The DNR, citing to 310 IAC 12-5-68, argues that this interpretation of the
rule is erroneous because the SMCRA clearly requires that a miner return the
land to its pre-mining capability. We agree that the mined land must
be returned to a condition that is at least as good as existed
prior to mining. However, the revegetation requirements found in 310 IAC 12-5
are specifically directed to the approved post-mining land uses and are the method
by which the goal set forth in 310 IAC 12-5-68 of returning the
land to its premining condition are reached. For example, 310 Ind.Administrative Code
12-5-59(a) provides, Each person who conducts surface mining activities shall establish . .
. a diverse, effective, and permanent vegetative cover of the same seasonal variety
native to the area that supports the approved postmining land use. 310
IAC 12-5-59(a). Subsection (b) of that rule provides that [a]ll revegetation shall
be carried out in a manner . . . compatible with the approved
postmining land use . . . . 310 IAC 12-5-59(b). 310
Ind.Administrative Code 12-5-62 prescribes mulching and other soil stabilization practices that will provide
adequate soil erosion control to be replaced by perennial species approved by the
postmining land use. 310 IAC 12-5-62. Moreover, 310 Ind.Administrative Code 12-5-64.1
identifies how success is measured for revegetation with respect to approved postmining land
uses.
See 310 IAC 12-5-64.1. Therefore, we agree with the trial
court that the ALJs conclusion that attainment of the approved postmining land use,
as demonstrated by compliance with the revegetation requirements for that land use, insures
[sic] that the land will be restored to a condition capable of supporting
that use is correct and is a reasonable interpretation of the regulations .
. . . Record, p. 1130; see, e.g., Peabody, 620 N.E.2d at
930. Thus, the appropriate standard in determining whether subsoil must be removed
and replaced is 310 IAC 12-5-12.1.
The DNR further argues that the ALJ read 310 IAC 12-5-12.1(f) in isolation
from the rest of the statutes and regulations, and that in doing so
the ALJ mistakenly placed the burden of proof in denying the permit revision
on the DNR. Specifically, the DNR contends that pursuant to Ind. Code
§ 14-34-4-7(a), the burden is on the applicant, (here, Peabody) not the DNR,
to demonstrate that the proposed revisions comply with the requirements of SMCRA.
That statute provides, in pertinent part:
The applicant has the burden of establishing that the application complies with all
the requirements of this article. The director may not approve a permit
or revision application unless the application affirmatively demonstrates and the director finds the
following:
Ind. Code § 14-34-4-7(a)(2).
We agree that a mining applicant generally bears the burden of proving that
the proposed revision complies with the requirements of SMCRA. However, we note
that the ALJ did not shift the burden of proof in denying the
permit revision to the DNR: the ALJ merely remanded the permits to
the DNR so it could make appropriate findings regarding whether Peabody was required
to remove portions of the subsoil to comply with the revegetation requirements.
Moreover, as previously discussed, compliance with the revegetation requirements assures that a miner
reclaims the land to as good or better condition than existed prior to
mining. Therefore, by requiring that Peabody meet both the revegetation standards and
the land capability restoration requirement, the DNR used an erroneous legal standard in
requiring the removal of more than topsoil. Peabody cannot be required to
demonstrate compliance with the DNRs erroneous standard.
As set forth in 310 IAC 12-5-12.1(f), Peabodys proposal for removal and replacement
of topsoil only is in compliance with the regulation unless the DNR finds
that portions of the subsoil need to be removed to comply with the
revegetation requirements. The DNRs position that Peabody has the burden of persuading
it that portions of the subsoil do not need to be removed and
replaced ignores the plain language of the regulation, which provides that the director
of the DNR may require that portions of the subsoil be removed and
. . . redistributed . . . if he finds such subsoil layers
are necessary to comply with the revegetation requirements of 310 IAC 12-5.
310 IAC 12-5-12.5(f) (emphasis added).
Therefore, we hold that the trial court correctly affirmed the ALJs decision that
the DNR had applied an incorrect legal standard in requiring Peabody to replace
more than topsoil for land reclamation. See, e.g., Peabody, 629 N.E.2d
at 930.