Skip to content

Indiana Department of Transportation

< Back | Agency Home | Submit Events >

Search events. View events.
  Transportation, Indiana Department of Submit Events
Welcome to the IN.gov Calendar. Please use the Help button to the right for any assistance while using the Calendar.
Click for help in using calendar displays. Print the contents of the current screen.

Advanced Search (New Search)
  From:
  To:

 

 

 


Submit
Entry Details
Notify me if this event changes.Add this event to my personal calendar.Email this entry to a friend.
Go Back
[INDOT] Portion of Milton-Madison Bridge Slid Into Place; Preparations Continue for Main Slide
Start Date: 3/14/2014Start Time: 12:00 AM
End Date: 3/14/2014
Entry Description
Portion of Bridge Slid Into Place; Preparations Continue for Main Slide

Next major task:
Workers plan to use four 200-ton jacks to lift the southeast corner of the new Milton-Madison Bridge steel truss in order to replace a steel bridge bearing, which dislodged on Tuesday, March 11. This will occur early during the week of March 17th and is one of the next steps necessary before the slide of the new steel truss can proceed.

The slide:
 A nearly 100-foot concrete bridge section over the Milton, Ky., riverbank was slid into place Thursday morning, March 13. Preparations are continuing to slide the nearly half-mile steel truss laterally 55 feet onto permanent piers. The schedule for the main truss slide has not been determined. Once the slide is completed, the bridge will remain closed while crews connect the bridge to the permanent approaches, which includes pouring concrete, installing expansion joints and pavement striping.

The ferry:
 A ferry is on the scene and will provide transportation across the river for emergency vehicles, such as an ambulance. Residents are asked to keep Ferry Street and the boat ramps clear on both sides of the river.

Dislodged bearing:  As work was taking place early Tuesday morning, March 11, a truss bearing, located at the southeast corner of the bridge, dislodged causing a 12-inch displacement of the truss. The bearing assembly consists of layers of steel plates and a polymer pad.

Closure:
 U.S. 421 will remain closed across the Ohio River between Madison, Ind., and Milton until the slide is completed and all roadway connections have been made. The anticipated opening date has not been determined but will be announced after the steel truss slide has completed. Signage is detouring traffic to the Markland Locks and Dam Bridge, connecting Kentucky Route 1039 and Indiana State Road 101, 26 miles upstream, or the I-65 Kennedy Bridge in Louisville, 46 miles downstream.

Updates:
 As updates become available, they will be posted on the project’s website, miltonmadisonbridge.com and via Twitter at twitter.com/mmbridgeproject. Regular updates will also be provided to local news media.

The Milton-Madison Bridge Project is a joint effort between the Indiana Department of Transportation and Kentucky Transportation Cabinet. The new steel truss bridge is 2,428 feet long and 40 feet wide with two 12-foot lanes and eight-foot shoulders – twice as wide as the old bridge.
Default
Entry Type:
Press Release
Entry Category:
  • Alerts and Notification
  • IN.gov Category:
  • Visiting & Playing
  • Agency Name
    Transportation, Indiana Department of

    Calendar software powered by Active Data Calendar   
    Select item(s) to Search






    Select item(s) to Search
    Select item(s) to Search

    Select item(s) to Search